Deva-Orastie Bypass Deva-Orastie


2011

Bridge Foundations Deva-Orastie Bypass

Deva-Orastie Bypass, Deva-Orastie, Romania

A part of the PanEuropean Corridor no. 5 was divided into 2 lots and one of those was appointed to Strabag. Bauer Romania was employed for the execution of Kelly piles dia. 1180 mm for 15 bridge foundations, one of them being the second longest one in Romania (bridge over Mures river). Due to difficult conditions - the foundations were influenced by the river level - we had to install secant pile pits dia. 620 mm. Drillings through cemented sand and sandstone layers were required.