Holrom Windfarm Park Sacele


2012

Pile Testing Holrom Windfarm Park

Holrom Windfarm Park, Sacele, Romania

The Holrom company was intending to build a windgenerator park in Sacele, Dobrogea Area. Bauer performed static compression and tension load tests on 3 locations where piles are needed, for loads up to 4500 kN. For each location 5 Kelly piles dia.
880 mm down to 15 - 24 m, using a BG 15 drilling rig, were installed. Later on, the design will be revised and the execution of the foundations will start.